City project
Airport Microgrid Study
Solar-and-battery microgrid analysis associated with the airport, including potential interconnection with the Regional Water Quality Control Plant and an airport charging hub.
- Current status
- Separate consultant analysis is underway or planned.
- Location
- Palo Alto Airport, Palo Alto, CA
July 9, 2025 commission feedback
Public commenters urged development of a solar-and-storage buildout. Commissioners supported continued exploration but requested improved economic and resilience analysis; one commissioner suggested considering shared investment with water-quality-plant partners.
Read related coverageFebruary 5, 2025 microgrid study scope and commissioner feedback
Staff described three modeled configurations: airport loads only; airport plus the Regional Water Quality Control Plant across adjacent parcels; and an airport charging hub. Modeling will size equipment and assess costs and daily operational benefits under summer and winter conditions and multiple outage types. A longer outage of at least one week was anticipated for a later outage scenario.
Read related coverageSeptember 4, 2024 update
Staff said the airport analysis would examine longer-duration outages and coordinate resilience planning with the Office of Emergency Services; the wastewater treatment plant was identified as a potential critical-facility connection.