Airport Microgrid Study

Solar-and-battery microgrid analysis associated with the airport, including potential interconnection with the Regional Water Quality Control Plant and an airport charging hub.

Current status
Separate consultant analysis is underway or planned.
Location
Palo Alto Airport, Palo Alto, CA
Street view near Palo Alto Airport, Palo Alto, CA
Map of Palo Alto Airport, Palo Alto, CA
  1. July 9, 2025 commission feedback

    Public commenters urged development of a solar-and-storage buildout. Commissioners supported continued exploration but requested improved economic and resilience analysis; one commissioner suggested considering shared investment with water-quality-plant partners.

    Read related coverage
  2. February 5, 2025 microgrid study scope and commissioner feedback

    Staff described three modeled configurations: airport loads only; airport plus the Regional Water Quality Control Plant across adjacent parcels; and an airport charging hub. Modeling will size equipment and assess costs and daily operational benefits under summer and winter conditions and multiple outage types. A longer outage of at least one week was anticipated for a later outage scenario.

    Read related coverage
  3. September 4, 2024 update

    Staff said the airport analysis would examine longer-duration outages and coordinate resilience planning with the Office of Emergency Services; the wastewater treatment plant was identified as a potential critical-facility connection.

    Read related coverage