City project
Bware Park Project
Park improvement project including concrete work, playground installation, and light-pole installation.
- Current status
- Construction underway; most concrete work complete and final grading in progress.
- Location
- Bower Park
October 22, 2024: Artwork installation preparation
Artwork footings were expected in the following weeks.
Read related coverageSeptember 24, 2024: Construction progress update
Staff reported that concrete work was complete and that playground equipment and light poles had been installed.
Read related coverageAugust 27, 2024 construction update
Contractor was expected to begin playground-footing installation the following week.
Read related coverage