City project
Corporation Way and West Bayshore Road Stormwater Pump Station and Trunk Line Improvements
Stormwater pump station and trunk line improvements serving Corporation Way and West Bayshore Road.
- Current status
- Under construction; East Bayshore is reduced to one-direction traffic while groundwater and utility conflicts are addressed.
- Location
- East Bayshore, Corporation Way, and West Bayshore, Palo Alto, CA
October 22, 2026 capital construction update
High groundwater in a sand layer beneath a 34-inch gas main delayed the connection between the receiving pit and wet well. Staff completed injection grouting and began temporary dewatering to enable pipe installation. The West Bayshore wet well was fabricated and encased in concrete, and electrical-control components were installed. Staff expected East Bayshore to reopen in December under a best-case scenario.
Read related coverageApril 13, 2026 CIP update
Staff reported that the microtunneling component was completed in approximately four weeks, replacing a proposed open-cut installation approach. Daily settlement monitoring found no settlement exceeding the one-inch criterion.
Read related coverageApril 22, 2025 update
Staff described approximately 700 feet of pipe upsizing from 21 inches to 30 inches and a new 25-cfs pump station. The wet well was described as approximately 12 feet by 50 feet and 18 to 19 feet deep.
Read related coverageApril 7, 2025: Construction Contract Approved
Council approved the construction contract, related change-order authority, and associated Stormwater Management Fund budget amendment as part of the consent calendar.
Read related coverageDecember 2, 2024 contract amendment approval
Council approved a $77,360 engineering contract amendment and term extension.
Read related coverage
Comments