Skip to main content
City of Palo Alto sealPalo Alto Civic

City project

Corporation Way and West Bayshore Road Stormwater Pump Station and Trunk Line Improvements

Stormwater pump station and trunk line improvements serving Corporation Way and West Bayshore Road.

Current status
Three projects had been completed; staff reported that bids had been secured for three additional projects, including the West Bayshore work.
Location
West Bayshore, Palo Alto, CA
Street view near West Bayshore, Palo Alto, CA
Map of West Bayshore, Palo Alto, CA
  1. April 13, 2026 CIP update

    Staff reported that the microtunneling component was completed in approximately four weeks, replacing a proposed open-cut installation approach. Daily settlement monitoring found no settlement exceeding the one-inch criterion.

    Read related coverage
  2. April 22, 2025 update

    Staff described approximately 700 feet of pipe upsizing from 21 inches to 30 inches and a new 25-cfs pump station. The wet well was described as approximately 12 feet by 50 feet and 18 to 19 feet deep.

    Read related coverage
  3. April 7, 2025: Construction Contract Approved

    Council approved the construction contract, related change-order authority, and associated Stormwater Management Fund budget amendment as part of the consent calendar.

    Read related coverage