City project
Corporation Way and West Bayshore Road Stormwater Pump Station and Trunk Line Improvements
Stormwater pump station and trunk line improvements serving Corporation Way and West Bayshore Road.
- Current status
- Three projects had been completed; staff reported that bids had been secured for three additional projects, including the West Bayshore work.
- Location
- West Bayshore, Palo Alto, CA
April 13, 2026 CIP update
Staff reported that the microtunneling component was completed in approximately four weeks, replacing a proposed open-cut installation approach. Daily settlement monitoring found no settlement exceeding the one-inch criterion.
Read related coverageApril 22, 2025 update
Staff described approximately 700 feet of pipe upsizing from 21 inches to 30 inches and a new 25-cfs pump station. The wet well was described as approximately 12 feet by 50 feet and 18 to 19 feet deep.
Read related coverageApril 7, 2025: Construction Contract Approved
Council approved the construction contract, related change-order authority, and associated Stormwater Management Fund budget amendment as part of the consent calendar.
Read related coverage