Gas-pipeline replacement project installing approximately 3.5 miles of gas main.

Current status
Scheduled for completion by the end of March 2025.
Location
Middlefield Road between Linton and Hamilton, Palo Alto, CA
Street view near Middlefield Road between Linton and Hamilton, Palo Alto, CA
Map of Middlefield Road between Linton and Hamilton, Palo Alto, CA
  1. March 5, 2025 construction update

    Staff reported that replacement work had been completed at Town and Country and on an unclearly transcribed road, and that crews were installing the final pipe section on Middlefield Road between Linton and Hamilton.