Hamilton Avenue Storm Drain Capacity Upgrade
Storm-drain capacity upgrade intended to reduce flooding and ponding.
- Current status
- Phase 1 had been constructed in part, but Phase 2 was not installed because of construction deficiencies; staff anticipated further work could occur next year.
- Location
- Hamilton Avenue, Palo Alto, CA
October 22, 2026 capital update
Staff reported approximately 1,700 to 1,800 linear feet of 48-inch pipe installed in Phase 1, while retaining an existing 18-inch line to more than triple capacity in the area. Phase 2, roughly 2,000 linear feet between New and Center, was deferred while the City addresses contractor-related deficiencies that could harm the system. The project will not be complete before the rainy season, though staff expects the completed work to improve drainage.
Read related coverageJune 15, 2026 public comment
A public commenter expressed appreciation for the project's initiation and urged City outreach to Valley Water regarding continued support for Reach 2 flood protection.
Read related coverageOctober 6, 2025: Construction Contract Approved
Council approved the construction contract and related change-order authority through the consent calendar.
Read related coverageApril 22, 2025 update
Staff said the project had been advanced ahead of the West Road project because of its priority and would replace undersized 12-, 15-, and 18-inch pipes with a 48-inch pipe. A future project would connect a minimum 36-inch pipe on Center Drive, from Hamilton Avenue to Channing Avenue, into the 48-inch Hamilton pipe.
Read related coverage