Quarry Road Improvements and Transit Center Access project

Transportation-access improvements connecting Quarry Road and the Palo Alto Transit Center.

Current status
Reached 60% design.
Location
Palo Alto Transit Center; Quarry Road and El Camino Real; El Camino Park, Palo Alto, CA
Street view near Palo Alto Transit Center; Quarry Road and El Camino Real; El Camino Park, Palo Alto, CA
Map of Palo Alto Transit Center; Quarry Road and El Camino Real; El Camino Park, Palo Alto, CA
  1. November 9, 2026: 60% design review

    Staff presented the 60% design and described project goals of improving transit efficiency, reducing congestion, improving bicycle and pedestrian safety, and increasing active transportation. Staff said Council will ultimately approve the design and construction contract.

    Read related coverage
  2. October 28, 2026: 60% design review

    Staff presented 60% plans. The design budget increased from $878,000 to $1,005,000, including $127,000 for added scope. Option B, which raises bicycle lanes at two corners, was estimated to add about $284,000 and at least three months; staff sought feedback on retaining street-level bike lanes under Option A. Staff expects to revise plans during winter, conduct another engagement round in spring, and pursue a Caltrans encroachment permit.

    Read related coverage
  3. October 26, 2026 update

    The Planning and Transportation Commission was scheduled to discuss the project on October 28, 2026, followed by City Council discussion on November 9, 2026.

    Read related coverage
  4. June 8, 2026: Committee feedback reported

    A Councilmember reported committee concerns that the proposed roadway extension could worsen bicycle circulation and requested reexamination and concurrent bicycle improvements.

    Read related coverage
  5. May 4, 2026: MTC funding and budget amendment approved

    Council approved an MTC funding agreement supplement providing up to $1,000,000 and appropriated $1,000,000 in the FY 2026 Capital Improvement Fund.

    Read related coverage
  6. April 29, 2026: Community meeting announced

    Staff reported that Palo Alto voters approved Measure D by 74% in November 2024 to undedicate a portion of El Palo Alto Park for the proposal. An in-person community meeting was scheduled for May 7, 2026, at 7:00 p.m. at Palo Alto City Hall.

    Read related coverage
  7. January 24, 2026: Listed as a preliminary 2026 objective

    Staff identified implementation in partnership with Stanford University, Caltrans, and VTA among preliminary 2026 objectives.

    Read related coverage
  8. Council-agreement update

    Staff reported that an agreement with Stanford was expected to go to City Council at the end of September.

    Read related coverage
  9. August 11, 2025: MTC grant reported

    Council reported that MTC awarded a $4 million grant for design and environmental work.

    Read related coverage
  10. March 10, 2025 update

    Preliminary engineering and environmental clearance were identified for Q4. Staff said it was coordinating with Stanford on grants and design agreements, but transportation-team staffing gaps and transitions were affecting the pace.

    Read related coverage