Reach 2

San Francisco Creek flood-protection effort referred to as Reach 2.

Current status
Under development
Location
San Francisco Creek
Street view near San Francisco Creek
Map of San Francisco Creek
  1. October 26, 2026 preparedness update

    The San Francisquito Creek Joint Powers Authority was still formally defining the project. Staff said multiple widening elements would be needed before addressing the Pope-Chaucer bridge.

    Read related coverage
  2. September 9, 2026 update

    The Joint Powers Authority agreed to seek a search firm after its executive director resigned at the end of July and to work with Valley Water through a joint committee on Valley Water's potential role in Reach 2. An update was anticipated within a couple of months.

    Read related coverage
  3. August 19, 2026 public-comment update

    A public commenter asked the City to help a Valley Water-JPA working group clarify roles and advance negotiations for the flood-protection effort.

    Read related coverage
  4. September 8, 2025 update

    The Council received the beginning of a study-session update intended to raise awareness and seek feedback from community members and elected leaders.

    Read related coverage
  5. February 3, 2025 update

    Council announcement stated the San Francisquito Creek Joint Powers Authority expects to advance the project over the next couple of years and will provide opportunities for community input.

    Read related coverage
  6. January 25, 2025: Initial priority discussion

    A council member identified continued coordination and funding work as priorities.

    Read related coverage