- Current status
- Contract amendments approved June 9, 2025.
- Location
- Hamilton Avenue
April 13, 2026 proposed budget update
The proposed FY 2027 budget includes $1.405 million for the program.
Read related coverageOctober 20, 2025 funding and contingency approval
Council approved a $1,000,000 construction-contingency increase for SAK Construction, LLC and Addendum No. 13 increasing authorized project funding to $12.6 million.
Read related coverageJune 9, 2025 contract amendments approved
Council approved amendments to Jacobs Engineering Group, Tanner Pacific, and Carollo Engineers contracts. The estimated project cost increased from $8.9 million to $9.7 million.
Read related coverageApril 22, 2025 budget update
The proposed FY 2026 budget increases the project by $1.5 million for utility-connection issues and construction-cost escalation; staff stated the timeline had not changed.