- Current status
- Mobilization began July 14, 2025; completion is projected for approximately December 1, 2025.
- Location
- Mayfield
October 28, 2025 update
The north, largest field's turf installation is complete and sand and cork infill remain; work is underway on the smaller field, with safety-net replacement and new goals also planned. Staff are beginning December scheduling and will announce reopening once construction timing is confirmed.
Read related coverageSeptember 23, 2025 project status update
Staff reported that phased replacement is underway to maintain field availability while the turf study progresses.
Read related coverageJuly 22, 2025 construction update
FieldTurf is installing turf with cork infill. Staff said the schedule had moved about one week later than previously communicated and user groups were being kept informed.
Read related coverageJune 24, 2025 update
Staff anticipated a three-month construction window and said updates would be provided to the Playing Fields Ad Hoc and full commission at the next meeting.