Stanford Palo Alto Community Playing Fields Turf Replacement

Phased replacement of synthetic turf at the Stanford Palo Alto Community Playing Fields, also known as Mayfield.

Current status
Mobilization began July 14, 2025; completion is projected for approximately December 1, 2025.
Location
Mayfield
Street view near Mayfield
Map of Mayfield
  1. October 28, 2025 update

    The north, largest field's turf installation is complete and sand and cork infill remain; work is underway on the smaller field, with safety-net replacement and new goals also planned. Staff are beginning December scheduling and will announce reopening once construction timing is confirmed.

    Read related coverage
  2. September 23, 2025 project status update

    Staff reported that phased replacement is underway to maintain field availability while the turf study progresses.

    Read related coverage
  3. July 22, 2025 construction update

    FieldTurf is installing turf with cork infill. Staff said the schedule had moved about one week later than previously communicated and user groups were being kept informed.

    Read related coverage
  4. June 24, 2025 update

    Staff anticipated a three-month construction window and said updates would be provided to the Playing Fields Ad Hoc and full commission at the next meeting.