City project

Crescent Park Traffic Calming Project

Traffic-calming project in Crescent Park.

Current status
Deferred to the next fiscal year for Council consideration; Council will decide whether to proceed with 100% design.
Location
Crescent Park
Street view near Crescent Park
Map of Crescent Park
  1. August 12, 2026: Advanced to final design

    City Council approved the project with direction to minimize the size of a bulbout of particular interest.

    Read related coverage
  2. August 10, 2026: Final concept design approved with reduced bulb-out

    Council approved permanent Option 1 improvements at Southwood Drive and East Crescent Drive, modified to reduce the bulb-out to the minimum size necessary for the turning radius.

    Read related coverage
  3. May 27, 2026: Council consideration delayed

    Staff said the item had been bumped from Council agendas several times and no new Council date had been set.

    Read related coverage
  4. Scheduled commission return

    Staff said the previously continued project would return to the commission on September 24, 2025.

    Read related coverage
  5. April 30, 2025 postponement and accessibility update

    Staff met with a neighbor to better understand accessibility needs; a further update will be included in a future written staff report.

    Read related coverage
  6. March 12, 2025: pedestrian beacon reported complete

    Transportation staff reported receiving notice that the pedestrian beacon installation was complete and said staff would confirm its operation.

    Read related coverage
  7. February 12, 2025 transportation update

    Transportation staff anticipated presenting the project to the Commission in early April.

    Read related coverage
  8. October 30, 2024 update

    A commissioner reported community feedback meeting attendance and stated that the effort could return to the Commission in early 2025.

    Read related coverage