City project

El Camino Field Turf Replacement

Replacement of the existing synthetic turf field, with the replacement material to be determined after the City's turf study.

Current status
Construction contract approved.
Location
Stanford Palo Alto Community Playing Fields, Palo Alto, CA
Street view near Stanford Palo Alto Community Playing Fields, Palo Alto, CA
Map of Stanford Palo Alto Community Playing Fields, Palo Alto, CA
  1. January 27, 2026 Council liaison update

    The liaison reported that City Council approved replacing the synthetic turf at El Camino Park following the Commission's recommendation.

    Read related coverage
  2. December 16, 2025: Completion and reopening update

    Staff reported substantial completion on December 5. The work began in July, was delivered on time and on budget, and cost roughly $3.2 million. The fields reopened immediately for public use; staff reported positive feedback from local clubs.

    Read related coverage
  3. November 25, 2025: Opening targeted after punch-list completion

    Staff reported that installation was complete and that remaining work included north-field safety-netting replacement, light-pole pads, and additional signage. Staff anticipated programming, including tournament play, beginning December 6 if punch-list work was signed off.

    Read related coverage
  4. November 17, 2025: Replacement decision continued

    Council continued the decision on whether to replace the field with synthetic turf or pursue a natural-grass alternative.

    Read related coverage
  5. August 26, 2025: Construction update

    Staff established tree-protection buffers of 5 feet along the red-line area and 3 feet along yellow-line areas. Screening was added to fencing because autonomous-vehicle activity interfered with grading lasers; staff clarified that this had not delayed the project.

    Read related coverage
  6. June 9, 2025: Construction contract approved

    Council approved the FieldTurf USA construction contract, contingency, and related FY 2025 budget amendment as part of the consent calendar.

    Read related coverage
  7. March 25, 2025: Deferred pending turf study

    Staff stated that, pursuant to City Council direction, the replacement would not move forward until the turf study is complete.

    Read related coverage
  8. January 28, 2025 CIP update

    Staff said City analysis will consider Santa Clara County research, other cities' work, community input, and comparative usage of synthetic and natural fields before a recommendation goes to City Council.

    Read related coverage
  9. December 18, 2024 field replacement update

    Staff said the study would be completed in time for presentations to the Commission and City Council before the FY 2026 budget; summer implementation would depend on the Council-directed field-surface option and project feasibility.

    Read related coverage