City project
Palo Alto Avenue Quiet Zone Project
Rail-crossing quiet-zone infrastructure project at the Palo Alto Avenue crossing.
- Current status
- Medians were installed at the end of 2025, making the location eligible for a quiet-zone implementation application.
- Location
- Alma Street and Palo Alto Avenue train crossing, Palo Alto, CA
May 11, 2026 budget discussion update
Staff said it would return with a CIP update showing Measure K funding in FY 2027 and FY 2028, requiring reconsideration of effects on the grade-separation project.
Read related coverageMay 4, 2026 budget and schedule update
Staff stated that accelerated design could take about 10 to 11 months rather than a typical 18 months, subject to coordination with Caltrain and the California Public Utilities Commission.
Read related coverageJanuary 14, 2026 status update
Staff anticipated bringing quiet-zone implementation eligibility to Council in late February 2026.
Read related coverageApril 7, 2025 quiet-zone project update
Staff reported that quiet-zone project development is underway and announced an April 16, 2025 community meeting concerning quiet zones at three crossings south of Palo Alto Avenue.
Read related coverage