Traffic Garden project

Traffic Garden project.

Current status
Underway; staff hoped for completion in September 2025 and confirmed the facility was on track to open in fall 2025.
Location
Ventura Park, Palo Alto, CA
Street view near Ventura Park, Palo Alto, CA
Map of Ventura Park, Palo Alto, CA
  1. September 29, 2025: Installed bike-safety park recognized by proclamation

    The Council issued a proclamation recognizing the community initiative that advanced the project. The proclamation stated that the park, described as approximately two basketball courts in size, had been installed on September 15, 2025.

    Read related coverage
  2. August 26, 2025: Construction update

    Design and asphalt resurfacing were complete. Basketball-court work began August 26, 2025, with traffic-garden work to follow in sequence.

    Read related coverage
  3. March 25, 2025: Design work underway

    Staff reported that design work and finalization were underway. Staff did not yet have a public project webpage and planned to meet with the Transportation Department about future updates.

    Read related coverage
  4. September 24, 2024 update

    The Commission was told that the project is moving forward and is accepting funding through the Parks Foundation. A commissioner reported that the project was progressing and accepting funding through the Parks Foundation.

    Read related coverage